As a result of the findings and recommendations of the Royal Commission of Inquiry into the Canterbury Earthquake Swarm of 2010-2011 the New Zealand Government has introduced new legislation that will require the mandatory strengthening of all earthquake-prone buildings in New Zealand. An earthquake prone building is currently defined as a building that is less than one third the seismic strength of a new building. If an owner does not wish to strengthen their buildings then they must demolish them. Seismic retrofitting of buildings is a form of property development and as such, the decision to retrofit or not should be based on a robust and soundly conducted feasibility study. Feasibility studies on seismic retrofitting can be particularly challenging for a number of reasons thus making it difficult for owners to make informed and sound decisions relating to their earthquake prone buildings. This paper considers the concept and process of feasibility analysis as applied to earthquake prone buildings and discusses the current challenges posed by such feasibility studies. A number of recommendations are made in an attempt to help develop a best practice model for decision making relating to earthquake prone buildings."
Purpose - The purpose of this paper is to identify through the application of Actor Network Theory (ANT) the issues and impediments to the implementation of mandatory seismic retrofitting policies proposed by the New Zealand Government. In particular the tension between the heritage protection objectives contained in the Resource Management Act 1991 and the earthquake mitigation measures contained in the Building Act 2004 are examined.
Design/methodology/approach - The paper uses a case study approach based on the Harcourts Building in Wellington New Zealand and the case law relating to attempts to demolish this particular building. Use is made of ANT as a 'lens' to identify and study the controversies around mandatory seismic retrofitting of heritage buildings. The concept of translation is used to draw network diagrams.
As a result of the Christchurch Earthquake that occurred on 22nd February 2011 and the resultant loss of life and widespread damage, a Royal Commission of Enquiry was convened in April 2011. The Royal Commission recommended a number of significant changes to the regulation of earthquake prone building in New Zealand. Earthquake prone buildings are buildings that are deemed to be of insufficient strength to perform adequately in a moderate earthquake. In response to the Royal Commission recommendations the New Zealand Government carried out a consultative process before announcing proposed changes to the building regulations in August 2013. One of the most significant changes is the imposition of mandatory strengthening requirements for earthquake prone buildings on a national basis. This will have a significant impact on the urban fabric of most New Zealand towns and cities. The type of traditional cost benefit study carried out to date fails to measure these impacts and this paper proposes an alternative methodology based on the analysis of land use data and rating valuations. This methodology was developed and applied to a small provincial town in the form of a case study. The results of this case study and the methodology used are discussed in this paper.