An early swim lane diagram which visually distinguishes responsibilities for SCIRT's ECI process.
A presentation which explains that NZTA have adopted SCIRT's approach to utilities management and sets out the reasons why. This presentation was created in 2015.
A paper which outlines the observed damage to Christchurch City Council-owned retaining walls and the repair solutions developed.
A report which details the archaeological investigations carried out during the course of SCIRT project 11232, wastewater renewal work in Sorensens Place.
A document which stipulates SCIRT's minimum standard for managing the risks arising from working around services.
A report created by BRANZ, the University of Auckland and Constructing Excellence New Zealand which was commissioned by the Productivity Partnership. It examines the use of KPIs by a number of rebuild organisations.
A plan which describes how SCIRT is to carry out construction works. The first version of this plan was produced on 10 August 2011.
A paper which outlines the purpose and planned outcomes of the SCIRT Training Forum group.
An extract from SCIRT's Alliance Agreement, detailing SCIRT's objectives.
A management plan which describes how SCIRT will coordinate utility authorities and utility relocations.
An abstract which describes the content of Trent Beckman-Cross's full PhD thesis.
A manual which informs SCIRT AutoCAD users of all tools, utilities, keyboard shortcuts, and tips available within the SCIRT CAD System.
A detailed presentation prepared by SCIRT IST's commercial manager to inform Delivery Team commercial managers about the processes and requirements relating to SCIRT's commercial model.
A document which describes SCIRT's approach to quantifying the impact of its communications and community engagement activities.
A plan which defines the procurement activities to be applied to SCIRT and explains how those activities are to be undertaken to meet SCIRT objectives and requirements. The first version of this plan was produced on 14 September 2011.
A document describing the early warning system to alert team members of ground and structural movement at the Arch.
A handout which includes information about the For Real employer process, the pre-employment courses available, a cost and value analysis for employers and some questions and answers.
An outline, created in 2011, of the levels of service and condition of the horizontal infrastructure within the central city, providing a broad indication of damage, service levels provided to residents and business owners, and used to estimate the cost of repairs following the earthquake events.
A paper published in the Journal of Structural Integrity and Maintenance, 2016, Vol. 1, No. 2, 88-93, which outlines the importance of asset registers and level of service in the wake of a disaster.
A document that outlines how timely and accurate information relating to estimating, actual project costs, future commitments, and total forecast cost, will be managed and reported for each project phase in the programme.
A document which describes SCIRT's discoveries and processes regarding archaeological finds on worksites.
A document which outlines several of Drain Surgeons' safety initiatives; developed when carrying out CCTV operations.
A memorandum of understanding that sets out how SCIRT and InfraTrain planned to work together to build an industry training framework and skilled workforce.
A poster which illustrates each of SCIRT's eight critical risks.
A document created in 2011, demonstrating the design parameters for the rebuild of wastewater, storm water, water supply and roading in the central city.
A document outlining the methodology for rebuilding horizontal infrastructure in the central city, covering wastewater (local reticulation and trunk), wastewater pump stations, storm water (local reticulation and trunk), potable water, roads, and bridges.
A design guideline which provides guidance to designers on how to carry out a whole of life evaluation of rebuild options.
A document outlining how the rebuild of wastewater, water supply, storm water and roading infrastructure was to be managed and coordinated with other programmes of work in the central city.
A copy of the plan, developed in 2011, outlining the communication and community engagement that supported SCIRT's central city programme and kept Christchurch residents informed about this work.
A PDF copy of a spreadsheet used to identify the impacts of traffic management in the central city.