A plan which aims to ensure an environment of Zero Harm on SCIRT worksites. The first version of this plan was produced on 29 July 2011.
This document contains a list of the SCIRT GIS services, along with a brief description of what the groupings of layers were and why they were needed.
A plan which outlines the processes and IT applications and services required to manage the SCIRT programme. The first version of this plan was produced on 9 August 2011.
A plan which outlines how SCIRT is to carry out condition investigations and analysis. The first version of this plan was produced on 1 September 2011.
A plan which aims to ensure an environment of Zero Harm on SCIRT worksites. The first version of this plan was produced on 29 July 2011.
A plan which outlines how to manage the environmental impacts that result from SCIRT works. The first version of this plan was produced on 20 July 2011.
A copy of the plan, developed in 2011, outlining the communication and community engagement that supported SCIRT's central city programme and kept Christchurch residents informed about this work.
A plan which outlines the scope, approach and key deliverables for communications and stakeholder engagement for SCIRT. The first version of this plan was produced on 7 January 2013.
A plan which aims to ensure the SCIRT programme complies with set specifications, design and industry quality standards. The first version of this plan was produced on 20 July 2011.
A tool which outlines the eight critical risks applicable to the SCIRT programme, and sets out minimum standards for addressing these risks. This tool was created in 2014.
An example of the five year rebuild schedule map created as part of the prioritisation process detailing where and when construction would start. The data behind this map was updated every quarter.
Damage to a house in Richmond. Large cracks run along the edges of this internal wall, and pictures on the wall are crooked. The photographer comments, "Internal damage to walls".
A video of a presentation by Richard Conlin during the Community Resilience Stream of the 2016 People in Disasters Conference. The presentation is titled, "Resilience, Poverty, and Seismic Culture".The abstract for this presentation reads as follows: A strategy of resilience is built around the recognition that effective emergency response requires community involvement and mobilization. It further recognizes that many of the characteristics that equip communities to respond most effectively to short term emergencies are also characteristics that build strong communities over the long term. Building resilient communities means integrating our approaches to poverty, community engagement, economic development, and housing into a coherent strategy that empowers community members to engage with each other and with other communities. In this way, resilience becomes a complementary concept to sustainability. This requires an asset-based change strategy where external agencies meet communities where they are, in their own space, and use collective impact approaches to work in partnership. This also requires understanding and assessing poverty, including physical, financial, and social capital in their myriad manifestations. Poverty is not exclusively a matter of class. It is a complex subject, and different communities manifest multiple versions of poverty, which must be respected and understood through the asset-based lens. Resilience is a quality of a community and a system, and develops over time as a result of careful analysis of strengths and vulnerabilities and taking actions to increase competencies and reduce risk situations. Resilience requires maintenance and must be developed in a way that includes practicing continuous improvement and adaptation. The characteristics of a resilient community include both physical qualities and 'soft infrastructure', such as community knowledge, resourcefulness, and overall health. This presentation reviews the experience of some earlier disasters, outlines a working model of how emergency response, resilience, and poverty interact and can be addressed in concert, and concludes with a summary of what the 2010 Chilean earthquake tells us about how a 'seismic culture' can function effectively in communities even when government suffers from unexpected shortcomings.
Geospatial liquefaction models aim to predict liquefaction using data that is free and readily-available. This data includes (i) common ground-motion intensity measures; and (ii) geospatial parameters (e.g., among many, distance to rivers, distance to coast, and Vs30 estimated from topography) which are used to infer characteristics of the subsurface without in-situ testing. Since their recent inception, such models have been used to predict geohazard impacts throughout New Zealand (e.g., in conjunction with regional ground-motion simulations). While past studies have demonstrated that geospatial liquefaction-models show great promise, the resolution and accuracy of the geospatial data underlying these models is notably poor. As an example, mapped rivers and coastlines often plot hundreds of meters from their actual locations. This stems from the fact that geospatial models aim to rapidly predict liquefaction anywhere in the world and thus utilize the lowest common denominator of available geospatial data, even though higher quality data is often available (e.g., in New Zealand). Accordingly, this study investigates whether the performance of geospatial models can be improved using higher-quality input data. This analysis is performed using (i) 15,101 liquefaction case studies compiled from the 2010-2016 Canterbury Earthquakes; and (ii) geospatial data readily available in New Zealand. In particular, we utilize alternative, higher-quality data to estimate: locations of rivers and streams; location of coastline; depth to ground water; Vs30; and PGV. Most notably, a region-specific Vs30 model improves performance (Figs. 3-4), while other data variants generally have little-to-no effect, even when the “standard” and “high-quality” values differ significantly (Fig. 2). This finding is consistent with the greater sensitivity of geospatial models to Vs30, relative to any other input (Fig. 5), and has implications for modeling in locales worldwide where high quality geospatial data is available.
Knowing how to rapidly rebuild disaster-damaged infrastructure, while deciding appropriate recovery strategies and catering for future investment is a matter of core interest to government decision makers, utility providers, and business sectors. The purpose of this research is to explore the effects of decisions and outcomes for physical reconstruction on the overall recovery process of horizontal infrastructure in New Zealand using the Canterbury and Kaikoura earthquakes as cases. A mixed approach including a systematic review, questionnaire survey and semi-structured interviews is used to capture perspectives of those involved in reconstruction process and gain insights into the effect of critical elements on infrastructure downtime. Findings from this research will contribute towards advancements of a systems dynamics model considering critical decision-making variables across phases of the reconstruction process to assess how these variables affect the rebuild process and the corresponding downtime. This project will improve the ability to explore alternative resilience improvement pathways and test the efficacy of alternative means for facilitating a faster and better reconstruction process.
As a result of the Canterbury earthquakes, over 60% of the concrete buildings in the Christchurch Central Business District have been demolished. This experience has highlighted the need to provide guidance on the residual capacity and repairability of earthquake-damaged concrete buildings. Experience from 2010 Chile indicates that it is possible to repair severely damaged concrete elements (see photo at right), although limited testing has been performed on such repaired components. The first phase of this project is focused on the performance of two lightly-reinforced concrete walls that are being repaired and re-tested after damage sustained during previous testing.
A plan which sets out how SCIRT will carry out internal communication over the life of its programme of work. The first version of this plan was produced on 24 January 2011.
A plan which defines the framework for performance measurement to align SCIRT with the objectives from the Alliance Agreement objectives. The first version of this plan was produced on 20 August 2011.
A plan which defines the risk and opportunity management activities to be applied by SCIRT to meet SCIRT objectives. The first version of this plan was produced on 12 September 2011.
Damage to a house in Richmond. A large crack runs through a concrete patio. The photographer comments, "The concrete patio is broken into big slabs. Over the following week this subsided even further".
A plan which describes how SCIRT would manage the risks associated with rebuilding horizontal infrastructure within Christchurch's central city area. The first version of this plan was produced on 24 October 2013.
A plan which documents the process SCIRT will follow to identify and pass on learnings from its programme of work. The first version of this plan was produced on 21 June 2016.
The purpose of this research is to investigate men’s experiences of the 2016 7.8 magnitude Kaikōura earthquake and Tsunami. While, research into the impacts of the earthquake has been conducted, few studies have examined how gender shaped people’s experiences of this natural hazard event. Analysing disasters through a gender lens has significantly contributed to disaster scholarship in identifying the resilience and vulnerabilities of individuals and communities pre- and post-disaster (Fordham, 2012; Bradshaw, 2013). This research employs understandings of masculinities (Connell, 2005), to examine men’s strengths and challenges in responding, recovering, and coping following the earthquake. Qualitative inquiry was carried out in Northern Canterbury and Marlborough involving 18 face-to-face interviews with men who were impacted by the Kaikōura earthquake and its aftermath. Interview material is being analysed using thematic and narrative analysis. Some of the preliminary findings have shown that men took on voluntary roles in addition to their fulltime paid work resulting in long hours, poor sleep and little time spent with family. Some men assisted wives and children to high ground then drove into the tsunami zone to check on relatives or to help evacuate people. Although analysis of the findings is currently ongoing, preliminary findings have identified that the men who participated in the study have been negatively impacted by the 2016 Kaikōura earthquake. A theme identified amongst participants was an avoidance to seek support with the challenges they were experiencing due to the earthquake. The research findings align with key characteristics of masculinity, including demonstrating risky behaviours and neglecting self or professional care. This study suggests that these behaviours affect men’s overall resilience, and thus the resilience of the wider community.
This paper analyses the city of Christchurch, New Zealand, which has been through dramatic changes since it was struck by a series of earthquakes of different intensities between 2010 and 2011. The objective is to develop a deeper understanding of resilience by looking at changes in green and grey infrastructures. The study can be helpful to reveal a way of doing comparative analysis using resilience as a theoretical framework. In this way, it might be possible to assess the blueprint of future master plans by considering how important the interplay between green and grey infrastructure is for the resilience capacity of cities.
Based on a qualitative study of four organisations involving 47 respondents following the extensive 2010 – 2011 earthquakes in Christchurch, New Zealand, this paper presents some guidance for human resource practitioners dealing with post-disaster recovery. A key issue is the need for the human resource function to reframe its practices in a post-disaster context, developing a specific focus on understanding and addressing changing employee needs, and monitoring the leadership behaviour of supervisors. This article highlights the importance of flexible organisational responses based around a set of key principles concerning communication and employee perceptions of company support.
INTRODUCTION This project falls under the Flagship 3: Wellington Coordinated Project. It supports other projects within FP3 to create a holistic understanding of risks posed by collapsed buildings due to future earthquake/s and the secondary consequences of cordoning in the short, mid and long term. Cordoning of the Christchurch CBD for more than two years and its subsequent implications on people and businesses had a significant impact on the recovery of Christchurch. Learning from this and experiences from the Kaikōura earthquake (where cordons were also established around selected buildings, Figure 3) have highlighted the need to understand the effects of cordons and plan for it before an earthquake occurs
Background This study examines the performance of site response analysis via nonlinear total-stress 1D wave-propagation for modelling site effects in physics-based ground motion simulations of the 2010-2011 Canterbury, New Zealand earthquake sequence. This approach allows for explicit modeling of 3D ground motion phenomena at the regional scale, as well as detailed nonlinear site effects at the local scale. The approach is compared to a more commonly used empirical VS30 (30 m time-averaged shear wave velocity)-based method for computing site amplification as proposed by Graves and Pitarka (2010, 2015), and to empirical ground motion prediction via a ground motion model (GMM).
A video of a presentation by Dr Sarah Beaven during the Social Recovery Stream of the 2016 People in Disasters Conference. The presentation is titled, "Leading and Coordinating Social Recovery: Lessons from a central recovery agency".The abstract for this presentation reads as follows: This presentation provides an overview of the Canterbury Earthquake Recovery Authority's Social Recovery Lessons and Legacy project. This project was commissioned in 2014 and completed in December 2015. It had three main aims: to capture Canterbury Earthquake Recovery Authority's role in social recovery after the Canterbury earthquakes, to identify lessons learned, and to disseminate these lessons to future recovery practitioners. The project scope spanned four Canterbury Earthquake Recovery Authority work programmes: The Residential Red Zone, the Social and Cultural Outcomes, the Housing Programme, and the Community Resilience Programme. Participants included both Canterbury Earthquake Recovery Authority employees, people from within a range of regional and national agencies, and community and public sector organisations who worked with Canterbury Earthquake Recovery Authority over time. The presentation will outline the origin and design of the project, and present some key findings.
A video of a presentation by Jane Morgan and Annabel Begg during the Social Recovery Stream of the 2016 People in Disasters Conference. The presentation is titled, "Monitoring Social Recovery in Greater Christchurch".The abstract for this presentation reads as follows: This presentation provides an overview of the Canterbury Earthquake Recovery Authority's Social Recovery Lessons and Legacy project. This project was commissioned in 2014 and completed in December 2015. It had three main aims: to capture Canterbury Earthquake Recovery Authority's role in social recovery after the Canterbury earthquakes, to identify lessons learned, and to disseminate these lessons to future recovery practitioners. The project scope spanned four Canterbury Earthquake Recovery Authority work programmes: The Residential Red Zone, the Social and Cultural Outcomes, the Housing Programme, and the Community Resilience Programme. Participants included both Canterbury Earthquake Recovery Authority employees, people from within a range of regional and national agencies, and community and public sector organisations who worked with Canterbury Earthquake Recovery Authority over time. The presentation will outline the origin and design of the project, and present some key findings.
A plan which proactively addresses the risk of fraud and lays out the actions that SCIRT will take when any suspected fraud is reported or discovered. The first version of this plan was produced on 12 February 2014.