An authority granted by the New Zealand Historic Places Trust, providing the authority to carry out earthquake repair work that may affect archaeological sites within the Christchurch City area.
A PDF copy of the official magazine for the 2010 City 2 Surf event.
A PDF copy of the official magazine for the 2011 City 2 Surf event.
A PDF copy of a publication promoting businesses in the city centre.
A PDF copy of a publication promoting businesses in the city centre.
A pdf copy of feedback given by the One Voice Te Reo Kotahi organising group on the draft Christchurch City Preliminary Resilience Assessment.
A document created in 2011, demonstrating the design parameters for the rebuild of wastewater, storm water, water supply and roading in the central city.
A document outlining the methodology for rebuilding horizontal infrastructure in the central city, covering wastewater (local reticulation and trunk), wastewater pump stations, storm water (local reticulation and trunk), potable water, roads, and bridges.
A PDF copy of a spreadsheet used to identify the impacts of traffic management in the central city.
A copy of the plan, created in 2011, detailing how the rebuild of the three waters and road infrastructure was to be coordinated with other utility operators.
A copy of the plan, developed in 2011, outlining the communication and community engagement that supported SCIRT's central city programme and kept Christchurch residents informed about this work.
A diagram created in 2011, showing the communication structure across rebuild agencies.
An outline, created in 2011, of the levels of service and condition of the horizontal infrastructure within the central city, providing a broad indication of damage, service levels provided to residents and business owners, and used to estimate the cost of repairs following the earthquake events.
A document outlining how the rebuild of wastewater, water supply, storm water and roading infrastructure was to be managed and coordinated with other programmes of work in the central city.
A diagram illustrating how the rebuild of the three waters and roading infrastructure was to be managed and coordinated with other programmes of work in the central city.
A plan which describes how SCIRT would manage the risks associated with rebuilding horizontal infrastructure within Christchurch's central city area. The first version of this plan was produced on 24 October 2013.
A paper which outlines SCIRT's approach to asset assessment, design and repair of damaged retaining walls, and presents a case study of a retaining wall rebuild, on Cunningham Terrace, Lyttelton.
A brochure created for Beca Heritage Week 2014, outlining SCIRT's repair work on heritage structures in the Central City. It was handed out to members of the public at SCIRT's walk and talk tours.
A copy of the plan developed in 2011 to facilitate a collaborative approach between all stakeholders and minimise the impact on the traffic network, because of the extensive repair works necessary to repair vertical and horizontal infrastructure.
A paper prepared for the Bulletin of the New Zealand Society for Earthquake Engineering, Vol. 44, no. 4, December 2011.
General Manager of Community Services for the Christchurch City Council Michael Aitken writes about the 2010 Canterbury Earthquake.
A PDF copy of a 'chapbook' featuring selected writings of "some of Canterbury's most exciting young writers, aged 10-15 years". The booklet was created for the WORD Christchurch Writers and Readers Festival 2014 with the support of All Right?, The School for Young Writers, Christchurch City Libraries, and WORD Christchurch.
A PDF copy of a letter from the Anglican Advocacy (formerly the Anglican Life Social Justice Unit), to Christchurch City Council requesting exemption from parking requirements for inner city east landowners.
A copy of a letter from Empowered Christchurch to Peter Sparrow, Director of Building Control and Rebuild at the Christchurch City Council, sent on 23 October 2014. The letter is a response to another letter sent by Peter Sparrow to Empowered Christchurch regarding existing use rights and exemptions from a building consent. In this letter, Empowered Christchurch requests furthur clarification from the Christchurch Building Consent Authority about these concepts.
A shortened version of a presentation created in 2011, outlining the approach to the central city rebuild.
A web story about the return of the stone lions to the Memorial Arch.
A document containing examples of newsletters printed and distributed to the inner city businesses and residents, to prepare them for the upcoming SCIRT rebuild work and update them on the positive progress being made.
A blog post from US Ambassador to New Zealand and Samoa, David Huebner, titled, "Independence Day in Christchurch".
A paper which outlines the observed damage to Christchurch City Council-owned retaining walls and the repair solutions developed.
A PDF copy of a poster promoting the 'Write Now' 2014 young writers workshops. Some of the best works from the workshop were published in a chapbook and in posters for Christchurch 2014 WORD Festival. The workshops were supported by All Right?, Christchurch City Libraries and The School for Young Writers.